Considering 3 m long 1 No. strainer
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 3 m long 40 mm dia PVC strainer Cost of 40 mm dia strainer | 1 | no | 400 | each | 400 | 400 | |
| 2 | Ordinary labour Labour cost for sinking and other costs | 1 | LS | 550 | per day | 171.88 | 171.88 | |
| Sub-Total | 571.88 | |||||||
| Contractor's Profit | 10% | 0.1 | 57.19 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 20.02 | |||||
| Total | 649.09 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 52.63 | ||||
| Grand Total | 701.72 | |||||||
| Rate per each | 702 | |||||||
| Rate per each | 702 | |||||||