Considering 1 rft
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm dia C-Class water- grade pipe 50 mm dia uPVC pipe | 1 | rft | 90 | foot | 90 | 90 | |
| 2 | Ordinary labour Labour for sinking and other costs | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 145 | |||||||
| Contractor's Profit | 10% | 0.1 | 14.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 5.08 | |||||
| Total | 164.58 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 13.34 | ||||
| Grand Total | 177.92 | |||||||
| Rate per rft | 178 | |||||||
| Rate per rm | 584.02 | |||||||