Breakup

28.1.2 75 mm N.D (88.90 mm O.D) M.S pipe, weight of min 10.1 kg/m, standard test pressure 176 kg/ m2, wall thickness of min 4.85 mm

Considering 100 rft of pipe line

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 75 mm ND (88.90 mm OD) Cost of pipe 100 rft 400 per foot 400 40000
2 4" x 400' Black tape Cost of tape: 4" x 400'-0" 1 roll 6370 per roll 6370 6370
3 Primer Cost of primer 1.136 liter 700 per litre 700 795.2
4 Earthwork in excavation Cutting trenches 100'-0" x 1'-6" x 3'-0"= 450.00 cft 450 cft 4979.17 % 0 cft 4.98 2241
5 Ordinary labour Laying and back-filling in/c levelling the top surface with excavated earth 100 rft 550 per day 25.57 2557
6 Skilled labour Skilled labour for applying primer, wrapping the pipe with tap in/c scrapping 100 rft 600 per day 15 1500
7 Demarkation with 8" x 8" C.C./MS plate LS 500
8 Carrying from Titas Gas store to work side in/c loading & unloading LS 500
Sub-Total 54463.2
Contractor's Profit 10% 0.1 5446.32
Contractor's Overhead Expenses 3.5% 0.035 1906.21
Total 61815.73
Add VAT with adjustment factor. 1.08108 7.5% 0.075 5012.08
Grand Total 66827.81
Rate per rft 668.28
Rate per rm 2192.63