Considering 100 rft of pipe line
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 mm ND (60.30 mm OD) Cost of pipe | 100 | rft | 215 | per foot | 215 | 21500 | |
| 2 | 2" x 200' Black tape Cost of tape: 2" x 200'-0" | 3 | roll | 1270 | per roll | 1270 | 3810 | |
| 3 | Primer Cost of primer | 0.757 | liter | 700 | per litre | 700 | 529.9 | |
| 4 | Earthwork in excavation Cutting trenches: 100'-0" x 1'-6" x 3'-0"= 450.00 cft | 450 | cft | 4979.17 | % 0 cft | 4.98 | 2241 | |
| 5 | Ordinary labour Laying and back-filling in/c levelling the top surface with excavated earth | 100 | rft | 550 | per day | 25.57 | 2557 | |
| 6 | Skilled labour Skilled labour for applying primer, wrapping the pipe with tap in/c scrapping | 100 | rft | 600 | per day | 15 | 1500 | |
| 7 | Demarkation with 8" x 8" C.C./MS plate | LS | 500 | |||||
| 8 | Carrying from Titas Gas store to work side in/c loading & unloading | LS | 400 | |||||
| Sub-Total | 33037.9 | |||||||
| Contractor's Profit | 10% | 0.1 | 3303.79 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 1156.33 | |||||
| Total | 37498.02 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 3040.38 | ||||
| Grand Total | 40538.4 | |||||||
| Rate per rft | 405.38 | |||||||
| Rate per rm | 1330.05 | |||||||