Breakup

28.1.3 50 mm N.D. (60.30 mm O.D) M.S pipe, weight of min 6.17 kg/m, standard test pressure 176 kg/ m2, wall thickness of min 4.47 mm

Considering 100 rft of pipe line

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 mm ND (60.30 mm OD) Cost of pipe 100 rft 215 per foot 215 21500
2 2" x 200' Black tape Cost of tape: 2" x 200'-0" 3 roll 1270 per roll 1270 3810
3 Primer Cost of primer 0.757 liter 700 per litre 700 529.9
4 Earthwork in excavation Cutting trenches: 100'-0" x 1'-6" x 3'-0"= 450.00 cft 450 cft 4979.17 % 0 cft 4.98 2241
5 Ordinary labour Laying and back-filling in/c levelling the top surface with excavated earth 100 rft 550 per day 25.57 2557
6 Skilled labour Skilled labour for applying primer, wrapping the pipe with tap in/c scrapping 100 rft 600 per day 15 1500
7 Demarkation with 8" x 8" C.C./MS plate LS 500
8 Carrying from Titas Gas store to work side in/c loading & unloading LS 400
Sub-Total 33037.9
Contractor's Profit 10% 0.1 3303.79
Contractor's Overhead Expenses 3.5% 0.035 1156.33
Total 37498.02
Add VAT with adjustment factor. 1.08108 7.5% 0.075 3040.38
Grand Total 40538.4
Rate per rft 405.38
Rate per rm 1330.05