Breakup

28.3.1 50 mm x 50 mm x 50 mm (N.D) equal tee

Considering 1 No. Tee

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 x 50 x 50 mm N.D. Tee CD40 Equal Tee (as per Titas Gas rate) 1 each 227 each 227 227
2 Ordinary labour Carrying charge 1 LS 550 per day 9.11 9.11
Sub-Total 236.11
Contractor's Profit 10% 0.1 23.61
Contractor's Overhead Expenses 3.5% 0.035 8.26
Total 267.98
Add VAT with adjustment factor. 1.08108 7.5% 0.075 21.73
Grand Total 289.71
Rate per each 290
Rate per each 290