Breakup

28.3.3 25 mm x 25 mm x 25 mm (N.D) equal tee

Considering 1 No. Tee

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 25 x 25 x 25 mm N.D. Tee CD40 Equal Tee (as per Titas Gas rate) 1 each 125 each 125 125
2 Ordinary labour Carrying charge 1 LS 550 per day 11 11
Sub-Total 136
Contractor's Profit 10% 0.1 13.6
Contractor's Overhead Expenses 3.5% 0.035 4.76
Total 154.36
Add VAT with adjustment factor. 1.08108 7.5% 0.075 12.52
Grand Total 166.88
Rate per each 167
Rate per each 167
Help