Breakup

28.3.9 50mm X 20 mm saddle

Considering 1 No. saddle

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 x 20 mm saddle Saddle (as per Titas Gas rate) 1 each 315 each 315 315
2 Ordinary labour Carrying charge 1 LS 550 per day 11 11
Sub-Total 326
Contractor's Profit 10% 0.1 32.6
Contractor's Overhead Expenses 3.5% 0.035 11.41
Total 370.01
Add VAT with adjustment factor. 1.08108 7.5% 0.075 30
Grand Total 400.01
Rate per each 400
Rate per each 400