Considering 1 No. saddle
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 x 20 mm saddle Saddle (as per Titas Gas rate) | 1 | each | 315 | each | 315 | 315 | |
| 2 | Ordinary labour Carrying charge | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 326 | |||||||
| Contractor's Profit | 10% | 0.1 | 32.6 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 11.41 | |||||
| Total | 370.01 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 30 | ||||
| Grand Total | 400.01 | |||||||
| Rate per each | 400 | |||||||
| Rate per each | 400 | |||||||