Breakup

28.3.10 50 mm dia end cap

Considering 1 No. end cap

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 mm dia end cap End cap (as per Titas Gas rate) 1 each 67 each 67 67
2 Ordinary labour Carrying charge 1 LS 550 per day 11 11
Sub-Total 78
Contractor's Profit 10% 0.1 7.8
Contractor's Overhead Expenses 3.5% 0.035 2.73
Total 88.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7.18
Grand Total 95.71
Rate per each 96
Rate per each 96