Breakup

28.3.11 25 mm dia end cap

Considering 1 No. end cap

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 25 mm dia end cap End cap (as per Titas Gas rate) 1 each 74 each 74 74
2 Ordinary labour Carrying charge 1 LS 550 per day 11 11
Sub-Total 85
Contractor's Profit 10% 0.1 8.5
Contractor's Overhead Expenses 3.5% 0.035 2.98
Total 96.48
Add VAT with adjustment factor. 1.08108 7.5% 0.075 7.82
Grand Total 104.3
Rate per each 104
Rate per each 104