Considering 1 No. end cap
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 mm dia end cap End cap (as per Titas Gas rate) | 1 | each | 74 | each | 74 | 74 | |
| 2 | Ordinary labour Carrying charge | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 85 | |||||||
| Contractor's Profit | 10% | 0.1 | 8.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 2.98 | |||||
| Total | 96.48 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 7.82 | ||||
| Grand Total | 104.3 | |||||||
| Rate per each | 104 | |||||||
| Rate per each | 104 | |||||||