Considering 1 No. equal Tee
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 x 50 mm equal tee Equal Tee (as per Titas Gas rate) | 1 | each | 10025 | each | 10025 | 10025 | |
| 2 | Ordinary labour Carrying, welding & fitting-fixing | 1 | LS | 550 | per day | 2557.5 | 2557.5 | |
| Sub-Total | 12582.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 1258.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 440.39 | |||||
| Total | 14281.14 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1157.93 | ||||
| Grand Total | 15439.07 | |||||||
| Rate per each | 15439 | |||||||
| Rate per each | 15439 | |||||||