Considering 1 No. Tee
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 25 x 25 x 25 mm service tee Service Tee (as per Titas Gas rate) | 1 | each | 3575 | each | 3575 | 3575 | |
| 2 | Ordinary labour Carrying, welding & fitting-fixing | 1 | LS | 550 | per day | 1650 | 1650 | |
| Sub-Total | 5225 | |||||||
| Contractor's Profit | 10% | 0.1 | 522.5 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 182.88 | |||||
| Total | 5930.38 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 480.84 | ||||
| Grand Total | 6411.22 | |||||||
| Rate per each | 6411 | |||||||
| Rate per each | 6411 | |||||||