Breakup

28.4.4 50 mm x 25 mm Service Tee

Considering 1 No. Tee

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 50 x 25 mm service tee Service Tee (as per Titas Gas rate) 1 each 8000 each 8000 8000
2 Ordinary labour Carrying, welding & fitting-fixing 1 LS 550 per day 2200 2200
Sub-Total 10200
Contractor's Profit 10% 0.1 1020
Contractor's Overhead Expenses 3.5% 0.035 357
Total 11577
Add VAT with adjustment factor. 1.08108 7.5% 0.075 938.67
Grand Total 12515.67
Rate per each 12516
Rate per each 12516