Considering 1 No. Tee
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 50 x 25 mm service tee Service Tee (as per Titas Gas rate) | 1 | each | 8000 | each | 8000 | 8000 | |
| 2 | Ordinary labour Carrying, welding & fitting-fixing | 1 | LS | 550 | per day | 2200 | 2200 | |
| Sub-Total | 10200 | |||||||
| Contractor's Profit | 10% | 0.1 | 1020 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 357 | |||||
| Total | 11577 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 938.67 | ||||
| Grand Total | 12515.67 | |||||||
| Rate per each | 12516 | |||||||
| Rate per each | 12516 | |||||||