Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Valve Pit (Titas Gas T&D Co. Ltd. design & plan.) (for 2" dia above) Valve pit as per Titas Gas T&D Co. Ltd. design | 1 | no | 48500 | each | 48500 | 48500 | |
| 2 | M.S. sheet cover supplied by Titas Gas T & D Co. Ltd.(for 2" dia above) M.S. sheet cover supplied by Titas Gas T&D Co. Ltd. | 1 | no | 20721 | each | 20721 | 20721 | |
| 3 | Earthwork in excavation Earth cutting | 405 | cft | 4979.17 | % 0 cft | 4.98 | 2016.9 | |
| 4 | One layer brick-flat soling Brick flat soling | 33.99 | sft | 36.19 | % sft | 0.36 | 12.24 | |
| 5 | Plain concrete (1:3:6) with brick chips Plain concrete (1:3:6) | 5.7783 | cft | 17561.67 | % cft | 175.62 | 1014.79 | |
| 6 | Brick work (1:6) in foundation Brick-work (1:6) | 62.26 | cft | 17397.25 | % cft | 173.97 | 10831.37 | |
| 7 | 1/2 " thick plaster (1:4) with N.C.F. Plaster with n.c.f. | 163.83 | sft | 28.39 | sft | 0.28 | 45.87 | |
| 8 | 38 mm thick artificial patent stone flooring (1:2:4) with brick chips 38 mm patent stone flooring (1:2:4),brick chips | 11.09 | sft | 4511.63 | % sft | 45.12 | 500.38 | |
| 9 | Sand fill (0.8) Sand filling (F.M. 0.8) | 275.51 | cft | 2692.67 | % cft | 26.93 | 7419.48 | |
| 10 | Ordinary labour Fitting-fixing & carrying of pit-cover | 1 | LS | 550 | per day | 8250 | 8250 | |
| 11 | Ordinary labour Labour for loading-unloading | 1 | LS | 550 | per day | 550 | 550 | |
| Sub-Total | 99862.03 | |||||||
| Contractor's Profit | 10% | 0.1 | 9986.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 3495.17 | |||||
| Total | 113343.4 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 9190 | ||||
| Grand Total | 122533.4 | |||||||
| Rate per no | 122533 | |||||||
| Rate per each | 122533 | |||||||