Breakup

28.8.1 12 mm N.D. with wall thickness 2 mm

Considering 100 rft of pipe line

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 12mm ND (20.0mm OD) Materials: Cost of pipe 100 rft 50 per foot 50 5000
2 Primer Cost of primer 0.57 liter 700 per litre 700 399
3 Ordinary labour Labour: Skilled labour for applying primer, in/c Fitting fixing and installtion 100 rft 550 per day 20 2000
4 Carrying from Titas Gas store to work side in/c loading & unloading LS 200
Sub-Total 7599
Contractor's Profit 10% 0.1 759.9
Contractor's Overhead Expenses 3.5% 0.035 265.97
Total 8624.87
Add VAT with adjustment factor. 1.08108 7.5% 0.075 699.31
Grand Total 9324.18
Rate per rft 93.24
Rate per rm 305.92