Considering 100 rft of pipe line
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12mm ND (20.0mm OD) Materials: Cost of pipe | 100 | rft | 50 | per foot | 50 | 5000 | |
| 2 | Primer Cost of primer | 0.57 | liter | 700 | per litre | 700 | 399 | |
| 3 | Ordinary labour Labour: Skilled labour for applying primer, in/c Fitting fixing and installtion | 100 | rft | 550 | per day | 20 | 2000 | |
| 4 | Carrying from Titas Gas store to work side in/c loading & unloading | LS | 200 | |||||
| Sub-Total | 7599 | |||||||
| Contractor's Profit | 10% | 0.1 | 759.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 265.97 | |||||
| Total | 8624.87 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 699.31 | ||||
| Grand Total | 9324.18 | |||||||
| Rate per rft | 93.24 | |||||||
| Rate per rm | 305.92 | |||||||