Breakup

28.8.2 20 mm N.D.with wall thickness 2.35 mm

Considering 100 rft of pipe line

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 20 mm ND (26.70 mm OD) Materials: Cost of pipe 100 rft 66 per foot 66 6600
2 Primer Cost of primer 0.57 liter 700 per litre 700 399
3 Ordinary labour Labour: Skilled labour for applying primer, in/c Fitting fixing and installtion 100 rft 550 per day 20 2000
4 Carrying from Titas Gas store to work side in/c loading & unloading LS 200
Sub-Total 9199
Contractor's Profit 10% 0.1 919.9
Contractor's Overhead Expenses 3.5% 0.035 321.97
Total 10440.87
Add VAT with adjustment factor. 1.08108 7.5% 0.075 846.56
Grand Total 11287.43
Rate per rft 112.87
Rate per rm 370.33