Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 12 x 6 mm gas stop cock Heavy type gas stop cock | 1 | no | 275 | each | 275 | 275 | |
| 2 | Ordinary labour Labour: | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 302.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 30.25 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.59 | |||||
| Total | 343.34 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 27.84 | ||||
| Grand Total | 371.18 | |||||||
| Rate per each | 371 | |||||||
| Rate per each | 371 | |||||||