Considering 1 No.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | 20 x 20 mm gas stop cock Heavy type gas stop cock | 1 | no | 500 | each | 500 | 500 | |
| 2 | Ordinary labour Labour | 1 | LS | 550 | per day | 45.83 | 45.83 | |
| Sub-Total | 545.83 | |||||||
| Contractor's Profit | 10% | 0.1 | 54.58 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 19.1 | |||||
| Total | 619.51 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 50.23 | ||||
| Grand Total | 669.74 | |||||||
| Rate per each | 670 | |||||||
| Rate per each | 670 | |||||||