Breakup

28.11 Testing and purging of the house line properly as per specifications Titas Gas T and D Co. Ltd. and accepted by the Engineer-in-charge.

Considering 1 meter of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Testing & purging Testing & purging the house line 1 meter 22 per meter 22 22
2 Testing & purging Incidental charges 1 - 22 per meter 2.2 2.2
Sub-Total 24.2
Contractor's Profit 10% 0.1 2.42
Contractor's Overhead Expenses 3.5% 0.035 0.85
Total 27.47
Add VAT with adjustment factor. 1.08108 7.5% 0.075 2.23
Grand Total 29.7
Rate per meter 30
Rate per meter 30