considering 1 no. set
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Cylinder heading line Cylinder heading line | 20 | nos | 12500 | each | 12500 | 250000 | |
| 2 | LP gas pigtal, ball valve and other necessary fittings LP gas pigtal, ball valve and other necessary fittings | 20 | nos | 2500 | each set | 2500 | 50000 | |
| 3 | MS seamless Schedule 40- 2" dia pipe line MS seamless Sch 40- 2" dia pipe line | 330 | rft | 1500 | per foot | 1500 | 495000 | |
| 4 | 1st stage regulator for gas line works First Stage Regulator | 1 | set | 150000 | each | 150000 | 150000 | |
| Sub-Total | 945000 | |||||||
| Contractor's Profit | 10% | 0.1 | 94500 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 33075 | |||||
| Total | 1072575 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 86965.45 | ||||
| Grand Total | 1159540.45 | |||||||
| Rate per set | 1159540 | |||||||
| Rate per set | 1159540 | |||||||