Breakup

28.13 Supplying and instalation of LP Gas Prepaid meter with smart recharging system. (Smart card for recharge gas, Meter connection, Second Stage Regulator, Gas meter header with individual valves (MS 150 class) in both ends of meter and other fittings etc. all complete and accepted by the Engineer-in-charge.

considering 1 no. set

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 LP gas prepaid meter with meter connection, second stage regulator, gas meter header with individual valves (MS 150 class) in both ends of meter and other fittings LS 20000
Sub-Total 20000
Contractor's Profit 10% 0.1 2000
Contractor's Overhead Expenses 3.5% 0.035 700
Total 22700
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1840.54
Grand Total 24540.54
Rate per set 24541
Rate per set 24541