Considering 10' x 10' x 10'= 1000 cft inside volume of room
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Ordinary labour Hire charge of spray machine in/c transportation and mobilization etc. | 1 | no | 550 | per day | 550 | 550 | |
| 2 | NEOCIDOL-60 NEOCIDOL-60 | 200 | ml | 165 | per % ml | 1.65 | 330 | |
| 3 | Skilled labour Skilled labour | 0.2 | no | 600 | per day | 600 | 120 | |
| 4 | Skilled technician Skilled technician | 0.05 | no | 1200 | per day | 1200 | 60 | |
| 5 | Ordinary labour Scaffolding, T&P and sundries etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| Sub-Total | 1087.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 108.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 38.06 | |||||
| Total | 1234.31 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 100.08 | ||||
| Grand Total | 1334.39 | |||||||
| Rate per cft | 1.33 | |||||||
| Rate per cum | 46.97 | |||||||