Considering 100 sft of work
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | DURS BAN 20 EC DURSBAN 20EC | 0.5 | liter | 1050 | per litre | 1050 | 525 | |
| 2 | Kerosene / Diesel Kerosene | 9.5 | liter | 68 | per litre | 68 | 646 | |
| 3 | Brush Brush | 1 | no | 10 | per foot | 10 | 10 | |
| 4 | Painter Painter | 0.33 | no | 700 | per day | 700 | 231 | |
| 5 | Ordinary labour Scaffolding, T&P and sundries, local carriage etc. | 1 | LS | 550 | per day | 55 | 55 | |
| Sub-Total | 1467 | |||||||
| Contractor's Profit | 10% | 0.1 | 146.7 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 51.35 | |||||
| Total | 1665.05 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 135 | ||||
| Grand Total | 1800.05 | |||||||
| Rate per sft | 18 | |||||||
| Rate per sqm | 193.75 | |||||||