Considering 1 No. nest.
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Earthwork in excavation Earth-work in excavation 1 x 1 m x 1.5 m x 1.5 m = 2.25 cum | 2.25 | cum | 4979.17 | % 0 cft | 175.84 | 395.64 | |
| 2 | DURS BAN 20 EC Cost of DURSBAN 20EC | 1.1 | liter | 1050 | per litre | 1050 | 1155 | |
| 3 | Skilled technician Skilled Technician | 0.25 | no | 1200 | per day | 1200 | 300 | |
| 4 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| Sub-Total | 2150.64 | |||||||
| Contractor's Profit | 10% | 0.1 | 215.06 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 75.27 | |||||
| Total | 2440.97 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 197.92 | ||||
| Grand Total | 2638.89 | |||||||
| Rate per nest | 2639 | |||||||
| Rate per nest | 2639 | |||||||