Breakup

30.5.1 Ground floor

Considering Area 10` x 10`

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Hollow block of 390mmx190mmx240mm 116 Nos 95 each 95 11020
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag 1.5 Bag 410 per bag 410 615
3 Sand (F.M. 1.2) 7 Cft 1900 per % cft 19 133
1 Head mason / Mosaic head mistry 0.1 Nos 800 per day 800 80
2 Mason / Mosaic mistry 1 Nos 700 per day 700 700
3 Ordinary labour 2.5 Nos 550 per day 550 1375
4 Scaffolding 25 Sft 10 per sft 10 250
5 Local carriage, sundries, T & P etc. LS 275
Sub-Total 14448
Contractor's Profit 10% 0.1 1444.8
Contractor's Overhead Expenses 3.5% 0.035 505.68
Total 16398.48
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1329.61
Grand Total 17728.09
Rate per Sft 177.28
Rate per sqm 1908.24
Help