Considering Volume
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Solid block of 240mmx114mmx70mm | 1100 | Nos | 13 | each | 13 | 14300 | |
| 2 | Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag | 5 | Bag | 410 | per bag | 410 | 2050 | |
| 3 | Sand (F.M. 1.2) | 32 | Cft | 1900 | per % cft | 19 | 608 | |
| 1 | Head mason / Mosaic head mistry | 0.1 | Nos | 800 | per day | 800 | 80 | |
| 2 | Mason / Mosaic mistry | 1 | Nos | 700 | per day | 700 | 700 | |
| 3 | Skilled labour | 1 | Nos | 600 | per day | 600 | 600 | |
| 4 | Ordinary labour | 1.5 | Nos | 550 | per day | 550 | 825 | |
| 5 | Ordinary labour Labour for soaking & cleaning blocks | 1 | Nos | 550 | per day | 550 | 550 | |
| 6 | Ordinary labour Labour for 7 days curing @ 1/8 labour per day | 0.875 | Nos | 550 | per day | 550 | 481.25 | |
| 7 | Scaffolding | 25 | Sft | 10 | per sft | 10 | 250 | |
| 8 | Local carriage, sundries, T & P etc. | LS | 275 | |||||
| Sub-Total | 20719.25 | |||||||
| Contractor's Profit | 10% | 0.1 | 2071.93 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 725.17 | |||||
| Total | 23516.35 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1906.73 | ||||
| Grand Total | 25423.08 | |||||||
| Rate per cft | 254.23 | |||||||
| Rate per cum | 8978.13 | |||||||