Breakup

30.15.1 Ground Floor

Considering Area 10` x 10`

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 390 mm x190 mm x112 mm sand cement Hollow Block (SCHB) 116 Nos 30 each 30 3480
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag 0.75 Bag 410 per bag 410 307.5
3 Sand (F.M. 1.2) 3.25 Cft 1900 per % cft 19 61.75
1 Head mason / Mosaic head mistry 0.1 Nos 800 per day 800 80
2 Mason / Mosaic mistry 1 Nos 700 per day 700 700
3 Ordinary labour 2.5 Nos 550 per day 550 1375
4 Scaffolding 25 Sft 10 per sft 10 250
5 Local carriage, sundries, T & P etc. LS 275
Sub-Total 6529.25
Contractor's Profit 10% 0.1 652.93
Contractor's Overhead Expenses 3.5% 0.035 228.52
Total 7410.7
Add VAT with adjustment factor. 1.08108 7.5% 0.075 600.87
Grand Total 8011.57
Rate per Sft 80.12
Rate per sqm 862.41
Help