Breakup

30.16.1 Ground floor

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag 0.65 cft 410 per bag 410 266.5
2 Sand (F.M. 1.2) Sand 4.1 cft 1900 per % cft 19 77.9
3 External plaster mix 0.086 liter 295 per litre 295 25.37
6 Ordinary labour Washing of sand, local carriage, scaffolding, curing & sundries etc. 1 LS 550 per day 275 275
4 Mason / Mosaic mistry 1 nos 700 per day 700 700
5 Ordinary labour 1.5 nos 550 per day 550 825
Sub-Total 2169.77
Contractor's Profit 10% 0.1 216.98
Contractor's Overhead Expenses 3.5% 0.035 75.94
Total 2462.69
Add VAT with adjustment factor. 1.08108 7.5% 0.075 199.68
Grand Total 2662.37
Rate per sft 26.62
Rate per sqm 286.54
Help