30.18 Supplying and placing of 60 mm thick coloured uni-block paving for walk way having size (222x110x60) mm, water absorption not greater than 4% and minimum compressive strength of 25 MPa on compacted sand bed of 50 mm on stabilized soil base, and filling all interstices with sand, cleaning etc. completed by the contractor and accepted by the Engineer-in-charge.

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 60 mm coloured Uni- block of 222mmx110mmx60mm 380 nos 20 each 20 7600
2 Sand (F.M. 0.8) 20 cft 1670 per % cft 16.7 334
3 Head mason / Mosaic head mistry 0.1 nos 800 per day 800 80
4 Mason / Mosaic mistry 0.5 nos 700 per day 700 350
5 Ordinary labour 1.5 nos 550 per day 550 825
6 Local carriage, sundries, T & P etc. LS 275
Sub-Total 9464
Contractor's Profit 10% 0.1 946.4
Contractor's Overhead Expenses 3.5% 0.035 331.24
Total 10741.64
Add VAT with adjustment factor. 1.08108 7.5% 0.075 870.94
Grand Total 11612.58
Rate per sft 116.13
Rate per sqm 1250.02