Breakup

30.26 Supplying and placing of 100 mm thick coloured uni-block for paving heavy trafic areas, road, industrial yard etc having size (222x110x100) mm, water absorption not greater than 4% and compressive strength of 40 MPa on compacted sand bed of 50 mm on stabilized soil base, and filling all interstices with sand, cleaning etc. completed by the contractor and accepted by the Engineer-in-charge.

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 100 mm Coloured Uni- block of 222mmx110mmx100mm 380 nos 34 each 34 12920
2 Sand (F.M. 0.8) 20 cft 1670 per % cft 16.7 334
3 Head mason / Mosaic head mistry 0.1 nos 800 per day 800 80
4 Mason / Mosaic mistry 0.5 nos 700 per day 700 350
5 Ordinary labour 1.5 nos 550 per day 550 825
6 Local carriage, sundries, T & P etc. LS 275
Sub-Total 14784
Contractor's Profit 10% 0.1 1478.4
Contractor's Overhead Expenses 3.5% 0.035 517.44
Total 16779.84
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1360.53
Grand Total 18140.37
Rate per sft 181.4
Rate per sqm 1952.59