Breakup

30.35.2.1 Ground floor

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 250 x 250 mm coloured engraved CC tiles 105 nos 60 per sft 60 6300
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement for pointing & jointing 1.1 bags 410 per bag 410 451
3 Sand (F.M. 1.2) 5.5 cft 1900 per % cft 19 104.5
4 Mason / Mosaic mistry 0.5 nos 700 per day 700 350
5 Ordinary labour 1.5 nos 550 per day 550 825
6 Local carriage, sundries, T & P etc. LS 275
Sub-Total 8305.5
Contractor's Profit 10% 0.1 830.55
Contractor's Overhead Expenses 3.5% 0.035 290.69
Total 9426.74
Add VAT with adjustment factor. 1.08108 7.5% 0.075 764.33
Grand Total 10191.07
Rate per sft 101.91
Rate per sqm 1096.96