Breakup

30.36.1.1 Ground floor

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 200 mm x 92 mm x 37.5 mm grey solid cladding block 480 nos 14 each 14 6720
3 Sand (F.M. 1.2) 16.25 cft 1900 per % cft 19 308.75
5 Scaffolding 25 sft 10 per sft 10 250
6 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag Cement 2.6 bags 410 per bag 410 1066
4 Ordinary labour Block work in/c screening sand and curring 100 sft 550 per day 33.55 3355
6 Local carriage, sundries, T & P etc. LS 275
Sub-Total 11974.75
Contractor's Profit 10% 0.1 1197.48
Contractor's Overhead Expenses 3.5% 0.035 419.12
Total 13591.35
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1102
Grand Total 14693.35
Rate per sft 146.93
Rate per sqm 1581.55
Help