Breakup

30.36.3.1 Ground floor

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 400 mm x 92 mm x 50 mm grey split cladding 220 nos 18 each 18 3960
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag 2.6 bags 410 per bag 410 1066
3 Sand (F.M. 1.2) 16.25 cft 1900 per % cft 19 308.75
5 Scaffolding 25 sft 10 per sft 10 250
4 Ordinary labour Cladding work in/c screening sand and curring 100 sft 550 per day 42.79 4279
6 Local carriage, sundries etc. LS 275
Sub-Total 10138.75
Contractor's Profit 10% 0.1 1013.88
Contractor's Overhead Expenses 3.5% 0.035 354.86
Total 11507.49
Add VAT with adjustment factor. 1.08108 7.5% 0.075 933.04
Grand Total 12440.53
Rate per sft 124.41
Rate per sqm 1339.15