Breakup

30.36.4.1 Ground floor

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 400 mm x 92 mm x 50 mm coloured split cladding 220 nos 23 each 23 5060
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag 2.6 bags 410 per bag 410 1066
3 Sand (F.M. 1.2) 16.25 cft 1900 per % cft 19 308.75
5 Scaffolding 25 sft 10 per sft 10 250
4 Ordinary labour Cladding work in/c screening sand and nominal curring 100 sft 550 per day 42.79 4279
6 Local carriage, sundries etc. LS 275
Sub-Total 11238.75
Contractor's Profit 10% 0.1 1123.88
Contractor's Overhead Expenses 3.5% 0.035 393.36
Total 12755.99
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1034.27
Grand Total 13790.26
Rate per sft 137.9
Rate per sqm 1484.36