Breakup

30.36.5.1 Ground floor

Considering Area 10` x 10` = 100 sft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 420 mm x 330 mm x 15 mm coloured facial cladding 67 nos 38 each 38 2546
2 Portland Composite Cement ,(CEM-II/B-M 42.5N (42.5MPa) (6-20% constituents other than clinker): 50 kg bag 2 bags 410 per bag 410 820
3 Sand (F.M. 1.2) 12.5 cft 1900 per % cft 19 237.5
5 Scaffolding 25 sft 10 per sft 10 250
4 Ordinary labour Cladding work in/c screening sand and curring 100 sft 550 per day 33.55 3355
6 Local carriage, sundries etc. LS 275
Sub-Total 7483.5
Contractor's Profit 10% 0.1 748.35
Contractor's Overhead Expenses 3.5% 0.035 261.92
Total 8493.77
Add VAT with adjustment factor. 1.08108 7.5% 0.075 688.68
Grand Total 9182.45
Rate per sft 91.82
Rate per sqm 988.35