Breakup

30.38.1.1 Ground floor

Considering Voulume = 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 AAC block of 600mmx200mmx240mm AAC block of 600mmx200mmx240mm 99 Nos 98 each 98 9702
2 Polymer Modified Adhesive Mortar (40 kgs bag) Polymer Modified Adhesive Mortar (40 kgs bag) 2.23 bag 700 per bag 700 1561
3 Head mason / Mosaic head mistry Labour Cost : Head Mason 0.25 no 800 per day 800 200
4 Mason / Mosaic mistry Mason 0.85 no 700 per day 700 595
5 Skilled labour Skilled labour 0.75 no 600 per day 600 450
6 Ordinary labour Ordinary Labour 1 no 550 per day 550 550
7 Ordinary labour Labour for cleaning & wet wiping of blocks 1 no 550 per day 550 550
8 Scaffolding Scaffolding 25 sft 10 per sft 10 250
9 Local carriage, sundries, T & P etc. LS 275
Sub-Total 14133
Contractor's Profit 10% 0.1 1413.3
Contractor's Overhead Expenses 3.5% 0.035 494.66
Total 16040.96
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1300.62
Grand Total 17341.58
Rate per cft 173.42
Rate per cum 6124.33