Breakup

30.38.2.1 Ground floor

Considering Voulume = 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 AAC block of 600mmx200mmx200mm AAC block of 600mmx200mmx200mm 119 Nos 90 each 90 10710
2 Polymer Modified Adhesive Mortar (40 kgs bag) Polymer Modified Adhesive Mortar (40 kgs bag) 2.23 bag 700 per bag 700 1561
3 Head mason / Mosaic head mistry Labour Cost : Head Mason 0.25 no 800 per day 800 200
4 Mason / Mosaic mistry Mason 0.9 no 700 per day 700 630
5 Skilled labour Skilled labour 0.75 no 600 per day 600 450
6 Ordinary labour Ordinary Labour 1 no 550 per day 550 550
7 Ordinary labour Labour for cleaning & wet wiping of blocks 1 no 550 per day 550 550
8 Scaffolding Scaffolding 25 sft 10 per sft 10 250
9 Local carriage, sundries, T & P etc. LS 275
Sub-Total 15176
Contractor's Profit 10% 0.1 1517.6
Contractor's Overhead Expenses 3.5% 0.035 531.16
Total 17224.76
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1396.6
Grand Total 18621.36
Rate per cft 186.21
Rate per cum 6576.01