Breakup

30.38.3.1 Ground floor

Considering Voulume = 100 cft of work

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 AAC block of 600mmx200mmx150mm AAC block of 600mmx200mmx150mm 156 Nos 82 each 82 12792
2 Polymer Modified Adhesive Mortar (40 kgs bag) Polymer Modified Adhesive Mortar (40 kgs bag) 2.23 bag 700 per bag 700 1561
3 Head mason / Mosaic head mistry Labour Cost : Head Mason 0.25 no 800 per day 800 200
4 Mason / Mosaic mistry Mason 1 no 700 per day 700 700
5 Skilled labour Skilled labour 0.75 no 600 per day 600 450
6 Ordinary labour Ordinary Labour 1 no 550 per day 550 550
7 Ordinary labour Labour for cleaning & wet wiping of blocks 1 no 550 per day 550 550
8 Scaffolding Scaffolding 25 sft 10 per sft 10 250
9 Local carriage, sundries, T & P etc. LS 275
Sub-Total 17328
Contractor's Profit 10% 0.1 1732.8
Contractor's Overhead Expenses 3.5% 0.035 606.48
Total 19667.28
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1594.64
Grand Total 21261.92
Rate per cft 212.62
Rate per cum 7508.68