Breakup

31.1 Mobilization and demobilization of boring equipment and man-power: at site (drilling rig comprising drilling pipe, drop hammer, tripod, pulley, chain, wrange, sample collection devices etc tools and plants; tripol for temporary camp, necessary work-force etc) (Once for one site)

Considering 1 No. site

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Truck fare within 20 km including loading & un-loading Truck fare in/c loading and unloading (both ways) 2 way 1850 per trip 1850 3700
2 Temporary camp at site for soil investigation work Camp at site 1 nos 1250 per site 1250 1250
3 Conveyance within 25 km Conveyance for man-power (2 x 6 nos) 12 nos 120 per day 120 1440
4 Foreman including site allowances Wages for man power : Foreman: 1 No. x (1/2 + 1/2) 1 manday 910 per day 910 910
5 Rig operators including site allowances Rig operators: 1 No. x (1/2 + 1/2) 1 manday 750 per day 750 750
6 Helper to rig operator/c site allowances Helper to rig operators: 4 nos x (1/2 + 1/2) 4 mandays 640 per day 640 2560
7 Ordinary labour Incidental, sundries etc. 1 LS 550 per day 400 400
Sub-Total 11010
Contractor's Profit 10% 0.1 1101
Contractor's Overhead Expenses 3.5% 0.035 385.35
Total 12496.35
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1013.22
Grand Total 13509.57
Rate per site 13510
Rate per site 13510