| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Foreman including site allowances Man-power : Foreman (1 x 1/16) | 0.06 | manday | 910 | per day | 910 | 54.6 | |
| 2 | Rig operators including site allowances Rig operators (1 x 1/8) | 0.13 | manday | 750 | per day | 750 | 97.5 | |
| 3 | Skilled labour Skilled labour (6 x 1/8) | 0.38 | manday | 600 | per day | 600 | 228 | |
| 4 | Ordinary labour Unskilled labour (2 x 1/8) | 0.25 | manday | 550 | per day | 550 | 137.5 | |
| 5 | Bamboo Material : Bamboo for platform (using 6 times) | 268 | rft | 13.5 | per foot | 2.25 | 603 | |
| 6 | Wooden plank (mango) Wooden plank (using 6times) 10 x 8'-0" x 12" x 1.5"=12 cft | 12 | cft | 700 | per cft | 116.67 | 1400.04 | |
| 7 | Rope Rope (using 4 times) | 8 | kg | 55 | per kg | 13.75 | 110 | |
| 8 | Small boat Hire charge of small boat | 1 | no | 850 | per day | 850 | 850 | |
| 9 | Skilled technician Boatman & helper | 1 | no | 1200 | per day | 1200 | 1200 | |
| 10 | Ordinary labour Tools & plant, sundries, consumables, local carrying | 1 | LS | 550 | per day | 2200 | 2200 | |
| Sub-Total | 6880.64 | |||||||
| Contractor's Profit | 10% | 0.1 | 688.06 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 240.82 | |||||
| Total | 7809.52 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 633.2 | ||||
| Grand Total | 8442.72 | |||||||
| Rate per bore hole | 8443 | |||||||
| Rate per bore hole | 8443 | |||||||