Breakup

31.13.1 Per test rate for conducting additional plate load test at the same site after first 03(Three) tests.

Considering Bearing capacity (tsf) = 5

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Field Engineer including site allowances: 1-3yrs Exp, Membersip with IEB Engineer 1 no 1900 per day 1900 1900
2 Foreman including site allowances Foreman 1 no 910 per day 910 910
3 Skilled labour Skilled labour 2 nos 600 per day 600 1200
4 Ordinary labour Ordinary labour 18 nos 550 per day 550 9900
5 Earthwork in excavation Earth work in exacavation 384 cft 4979.17 % 0 cft 0.5 192
6 Load testing result sheet preparation Preparation of test result in standard form in triplicate 1 test 6500 per test 6500 6500
7 Other incidental charge LS 800
Sub-Total 21402
Contractor's Profit 10% 0.1 2140.2
Contractor's Overhead Expenses 3.5% 0.035 749.07
Total 24291.27
Add VAT with adjustment factor. 1.08108 7.5% 0.075 1969.56
Grand Total 26260.83
Rate per test 5252.2
Rate per test 5252.2