Considering Bearing capacity (tsf) = 5
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Field Engineer including site allowances: 1-3yrs Exp, Membersip with IEB Engineer | 1 | no | 1900 | per day | 1900 | 1900 | |
| 2 | Foreman including site allowances Foreman | 1 | no | 910 | per day | 910 | 910 | |
| 3 | Skilled labour Skilled labour | 2 | nos | 600 | per day | 600 | 1200 | |
| 4 | Ordinary labour Ordinary labour | 18 | nos | 550 | per day | 550 | 9900 | |
| 5 | Earthwork in excavation Earth work in exacavation | 384 | cft | 4979.17 | % 0 cft | 0.5 | 192 | |
| 6 | Load testing result sheet preparation Preparation of test result in standard form in triplicate | 1 | test | 6500 | per test | 6500 | 6500 | |
| 7 | Other incidental charge | LS | 800 | |||||
| Sub-Total | 21402 | |||||||
| Contractor's Profit | 10% | 0.1 | 2140.2 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 749.07 | |||||
| Total | 24291.27 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1969.56 | ||||
| Grand Total | 26260.83 | |||||||
| Rate per test | 5252.2 | |||||||
| Rate per test | 5252.2 | |||||||