Breakup

31.15.1 Mobilization and demobilization of survey equipment and man-power: survey equipment comprising Total Station, RTK-GPS, level machine, Prism with stand, Tripod and others necessary tools & plants, triple for temporary camp and necessary work-force.

Considering 1 No. site

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Truck fare within 20 km including loading & un-loading Truck fare in/c loading and unloading (both ways) 2 way 1850 per trip 1850 3700
2 Temporary camp at site for soil investigation work Camp at site 1 nos 1250 per site 1250 1250
3 Conveyance within 25 km Conveyance for man-power (2 x 2 nos) 4 nos 120 per day 120 480
4 Surveyor (10yrs Exp / diploma Engineer trained in survey ) Wages for man power : Surveyor: 1 No. x (1/2 + 1/2) 1 manday 1400 per day 1400 1400
5 Helper to surveyor Helper to surveyor: 2 nos x (1/2 + 1/2) 2 mandays 800 per day 800 1600
6 Incidental, sundries etc. LS 100
Sub-Total 8530
Contractor's Profit 10% 0.1 853
Contractor's Overhead Expenses 3.5% 0.035 298.55
Total 9681.55
Add VAT with adjustment factor. 1.08108 7.5% 0.075 784.99
Grand Total 10466.54
Rate per site 10467
Rate per site 10467