Considering 1 Acre of Land
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Hire charge of total station Topographic & physical feature survey : Hire charge of Total Station. | 2 | day | 3000 | per day | 3000 | 6000 | |
| 2 | Surveyor (10yrs Exp / diploma Engineer trained in survey ) Wages for man power : Surveyor: 1 day field + 1 day processing | 1 | manday | 1400 | per day | 1400 | 1400 | |
| 3 | Autocad operator CAD operator: 1 day processing | 1 | manday | 1200 | per day | 1200 | 1200 | |
| 4 | Helper to surveyor Helper to surveyor:2 nos @ 1 day field | 2 | mandays | 800 | per day | 800 | 1600 | |
| 5 | A2 size printing A2 size Printing | 4 | copy | 150 | each | 150 | 600 | |
| 6 | Computer, Printer, Paper, incidental sundries etc. | LS | 400 | |||||
| Sub-Total | 11200 | |||||||
| Contractor's Profit | 10% | 0.1 | 1120 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 392 | |||||
| Total | 12712 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 1030.7 | ||||
| Grand Total | 13742.7 | |||||||
| Rate per acre | 13743 | |||||||
| Rate per acre | 13743 | |||||||