32.1 Stripping of unserviceable plaster including racking out joints, cleaning etc.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.25 no 600 per day 600 150
2 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
3 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 11 11
4 Ordinary labour T & P, scaffolding, ladder, sundries etc. 1 LS 550 per day 11 11
Sub-Total 309.5
Contractor's Profit 10% 0.1 30.95
Contractor's Overhead Expenses 3.5% 0.035 10.83
Total 351.28
Add VAT with adjustment factor. 1.08108 7.5% 0.075 28.48
Grand Total 379.76
Rate per sqm 38
Rate per sqm 38