Considering 10 sqm of works
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 0.25 | no | 600 | per day | 600 | 150 | |
| 2 | Ordinary labour Ordinary labour | 0.25 | no | 550 | per day | 550 | 137.5 | |
| 3 | Ordinary labour Brooming, cleaning etc. | 1 | LS | 550 | per day | 11 | 11 | |
| 4 | Ordinary labour T & P, scaffolding, ladder, sundries etc. | 1 | LS | 550 | per day | 11 | 11 | |
| Sub-Total | 309.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 30.95 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 10.83 | |||||
| Total | 351.28 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 28.48 | ||||
| Grand Total | 379.76 | |||||||
| Rate per sqm | 38 | |||||||