Breakup

32.2.1 Picking-up of unserviceable patent stone from floor and dado etc. and removal of debris to a safe distance.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
2 Skilled labour Skilled labour 0.5 no 600 per day 600 300
2 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
3 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 11 11
4 Ordinary labour T & P, sundries etc. 1 LS 550 per day 22 22
Sub-Total 470.5
Contractor's Profit 10% 0.1 47.05
Contractor's Overhead Expenses 3.5% 0.035 16.47
Total 534.02
Add VAT with adjustment factor. 1.08108 7.5% 0.075 43.3
Grand Total 577.32
Rate per sqm 57.7
Rate per sqm 57.7