Breakup

32.2.2 Picking-up of unserviceable tiles including bonding mortar from floor, walls and dado etc. and removal of debris to a safe distance.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.75 no 600 per day 600 450
2 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
3 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 11 11
4 Ordinary labour T & P, sundries etc. 1 LS 550 per day 22 22
Sub-Total 620.5
Contractor's Profit 10% 0.1 62.05
Contractor's Overhead Expenses 3.5% 0.035 21.72
Total 704.27
Add VAT with adjustment factor. 1.08108 7.5% 0.075 57.1
Grand Total 761.37
Rate per sqm 76.1
Rate per sqm 76.1
Help