Breakup

32.4 Dismantling of unserviceable/damaged terraced roof including beam, column, borga & tiles etc. and removal of debris to a safe distance.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.5 no 600 per day 600 300
2 Ordinary labour Ordinary labour 1 no 550 per day 550 550
3 Scaffolding Scaffolding 2.5 sqm 10 per sft 107.6 269
4 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 27.5 27.5
5 Ordinary labour T & P, sundries etc. 1 LS 550 per day 192.5 192.5
Sub-Total 1339
Contractor's Profit 10% 0.1 133.9
Contractor's Overhead Expenses 3.5% 0.035 46.87
Total 1519.77
Add VAT with adjustment factor. 1.08108 7.5% 0.075 123.22
Grand Total 1642.99
Rate per sqm 164.3
Rate per sqm 164.3