Considering 10 sqm of works
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 0.5 | no | 600 | per day | 600 | 300 | |
| 2 | Ordinary labour Ordinary labour | 1 | no | 550 | per day | 550 | 550 | |
| 3 | Scaffolding Scaffolding | 2.5 | sqm | 10 | per sft | 107.6 | 269 | |
| 4 | Ordinary labour Brooming, cleaning etc. | 1 | LS | 550 | per day | 27.5 | 27.5 | |
| 5 | Ordinary labour T & P, sundries etc. | 1 | LS | 550 | per day | 192.5 | 192.5 | |
| Sub-Total | 1339 | |||||||
| Contractor's Profit | 10% | 0.1 | 133.9 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 46.87 | |||||
| Total | 1519.77 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 123.22 | ||||
| Grand Total | 1642.99 | |||||||
| Rate per sqm | 164.3 | |||||||
| Rate per sqm | 164.3 | |||||||