Breakup

32.5.1.1 Dismantling of unserviceable/damaged brick works (with cement or lime mortar) of thickness 250 mm in foundation and superstructure and removal of debris to a safe distance.

Considering 3 cum of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 1 nos 600 per day 600 600
2 Ordinary labour Ordinary labour 1 nos 550 per day 550 550
3 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 27.5 27.5
4 Ordinary labour T & P, scaffolding, ladder, sundries etc. 1 LS 550 per day 137.5 137.5
Sub-Total 1315
Contractor's Profit 10% 0.1 131.5
Contractor's Overhead Expenses 3.5% 0.035 46.03
Total 1492.53
Add VAT with adjustment factor. 1.08108 7.5% 0.075 121.02
Grand Total 1613.55
Rate per cum 538
Rate per cum 538
Help