Considering 10 sqm of works
| SL | Item Name | Quantity | Unit | Item Rate (Taka) | Item Unit | Unit Price (Taka) | Sub Total (Taka) | |
|---|---|---|---|---|---|---|---|---|
| 1 | Skilled labour Skilled labour | 0.5 | nos | 600 | per day | 600 | 300 | |
| 2 | Ordinary labour Ordinary labour | 0.5 | nos | 550 | per day | 550 | 275 | |
| 3 | Ordinary labour Brooming, cleaning etc. | 1 | LS | 550 | per day | 16.5 | 16.5 | |
| 4 | Ordinary labour T & P, scaffolding, ladder, sundries etc. | 1 | LS | 550 | per day | 66 | 66 | |
| Sub-Total | 657.5 | |||||||
| Contractor's Profit | 10% | 0.1 | 65.75 | |||||
| Contractor's Overhead Expenses | 3.5% | 0.035 | 23.01 | |||||
| Total | 746.26 | |||||||
| Add VAT with adjustment factor. | 1.08108 | 7.5% | 0.075 | 60.51 | ||||
| Grand Total | 806.77 | |||||||
| Rate per sqm | 80.7 | |||||||
| Rate per sqm | 80.7 | |||||||