Breakup

32.5.1.2 Dismantling of unserviceable/damaged brick works (with cement or lime mortar) of thickness 75/125 mm in foundation and superstructure and removal of debris to a safe distance.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 0.5 nos 600 per day 600 300
2 Ordinary labour Ordinary labour 0.5 nos 550 per day 550 275
3 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 16.5 16.5
4 Ordinary labour T & P, scaffolding, ladder, sundries etc. 1 LS 550 per day 66 66
Sub-Total 657.5
Contractor's Profit 10% 0.1 65.75
Contractor's Overhead Expenses 3.5% 0.035 23.01
Total 746.26
Add VAT with adjustment factor. 1.08108 7.5% 0.075 60.51
Grand Total 806.77
Rate per sqm 80.7
Rate per sqm 80.7