Breakup

32.5.2 Dismantling of plain concrete made of lime or cement and removal of debris to a safe distance.

Considering 1 cum of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Skilled labour Skilled labour 1 nos 600 per day 600 600
2 Ordinary labour Ordinary labour 1 no 550 per day 550 550
3 Ordinary labour Brooming, cleaning etc. 1 LS 550 per day 27.5 27.5
4 Ordinary labour T & P, sundries etc. 1 LS 550 per day 165 165
Sub-Total 1342.5
Contractor's Profit 10% 0.1 134.25
Contractor's Overhead Expenses 3.5% 0.035 46.99
Total 1523.74
Add VAT with adjustment factor. 1.08108 7.5% 0.075 123.55
Grand Total 1647.29
Rate per cum 1647
Rate per cum 1647