Breakup

32.5.3 Dismantling of brick flat soling and removal of debris to a safe distance and removal of debris to a safe distance.

Considering 10 sqm of works

SL Item Name Quantity Unit Item Rate (Taka) Item Unit Unit Price (Taka) Sub Total (Taka)
1 Ordinary labour Ordinary labour 0.25 no 550 per day 550 137.5
2 Ordinary labour Removing /cleaning sand, soil from soling bed 1 LS 550 per day 16.5 16.5
3 Ordinary labour T & P, sundries etc. 1 LS 550 per day 18.32 18.32
Sub-Total 172.32
Contractor's Profit 10% 0.1 17.23
Contractor's Overhead Expenses 3.5% 0.035 6.03
Total 195.58
Add VAT with adjustment factor. 1.08108 7.5% 0.075 15.86
Grand Total 211.44
Rate per sqm 21.1
Rate per sqm 21.1